nerdexam
PMIPMI

PMI-RMP · Question #72

PMI-RMP Question #72: Real Exam Question with Answer & Explanation

The correct answer is B: Jo-Hari Window. See the full explanation below for the reasoning.

Perform Targeted Risk Analysis

Question

You are the project manager of a large project that will last four years. In this project, you would like to model the risk based on its distribution, impact, and other factors. There are three modeling techniques that a project manager can use to include both event-oriented and project- oriented analysis. Which modeling technique does NOT provide event-oriented and project- oriented analysis for identified risks?

Options

  • ASensitivity analysis
  • BJo-Hari Window
  • CExpected monetary value
  • DModeling and simulation

Topics

#Risk analysis techniques#Quantitative risk analysis#Qualitative risk analysis#Modeling and simulation

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions