nerdexam
PMIPMI

PMI-RMP · Question #73

PMI-RMP Question #73: Real Exam Question with Answer & Explanation

The correct answer is C: Monitoring and Controlling. See the full explanation below for the reasoning.

Risk Monitoring and Reporting

Question

You are the project manager of the GHY project for your company. This project has a budget of $543,000 and is expected to last 18 months. In this project, you have identified several risk events and created risk response plans. In what project management process group will you implement risk response plans?

Options

  • AExecuting
  • BPlanning
  • CMonitoring and Controlling
  • DIn any process group where the risk event resides

Topics

#Risk response implementation#PMBOK process groups#Monitoring risks#Risk management processes

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions