When does the Identify Risks process take place in a project?
Options
- AAt the Planning stage.
- BThroughout the project life-cycle.
- CAt the Initiating stage.
- DAt the Executing stage.
Topics
#Identify Risks#Risk Management Process#Project Life Cycle#Continuous Process