PMIPMI
PMI-RMP · Question #69
PMI-RMP Question #69: Real Exam Question with Answer & Explanation
The correct answer is D: Cost of the risk impact if the risk event occurs. See the full explanation below for the reasoning.
Perform Targeted Risk Analysis
Question
You are the project manager of the GHQ project for your company. You are working with your project team to prepare for the qualitative risk analysis process. Mary, a project team member, does not understand why you need to complete qualitative risks analysis. You explain to Mary that qualitative risks analysis helps you determine which risks needs additional analysis. There are also some other benefits that qualitative risks analysis can do for the project. Which one of the following is NOT an accomplishment of the qualitative risk analysis process?
Options
- ACorresponding impact on project objectives
- BTime frame for a risk response
- CPrioritization of identified risk events based on probability and impact
- DCost of the risk impact if the risk event occurs
Topics
#Qualitative Risk Analysis#Risk Prioritization#Risk Impact Assessment#Quantitative vs Qualitative Risk Analysis
Community Discussion
No community discussion yet for this question.