What should the risk owner use as an effective information-gathering technique during the planning session?

The correct answer is C. Brainstorming. Brainstorming is the foundational information-gathering technique used during planning sessions to identify and collect risk-related information from a group. It encourages free-form idea generation from team members, stakeholders, and subject matter experts, making it ideal…

Risk Strategy and Planning

Question

What should the risk owner use as an effective information-gathering technique during the planning session?

Options

  • AMonte Carlo analysis
  • BUpdate risk register
  • CBrainstorming
  • DCost and time estimating

How the community answered

(38 responses)
  • A
    3% (1)
  • B
    3% (1)
  • C
    89% (34)
  • D
    5% (2)

Explanation

Brainstorming is the foundational information-gathering technique used during planning sessions to identify and collect risk-related information from a group. It encourages free-form idea generation from team members, stakeholders, and subject matter experts, making it ideal for surfacing a wide range of potential risks early in planning. Monte Carlo analysis (A) is a quantitative simulation tool, not an information-gathering technique. Updating the risk register (B) is an output activity, not a gathering technique. Cost and time estimating (D) is an estimation activity, not an information-gathering method. Brainstorming is explicitly listed in the PMBOK as a primary risk identification and information-gathering technique.

Topics

#Information gathering#Risk identification#Brainstorming#Risk planning