nerdexam
PMIPMI

PMI-RMP · Question #624

PMI-RMP Question #624: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #624. The question stem and answer options stay visible for context.

Perform Targeted Risk Analysis

Question

it typically takes 5 hours to perform a complete home inspection. If there are unforeseen risk factors, it can take up to 7 hours to finish the inspection. The earliest the project team has ever finished an inspection is in 3 hours. Using the project evaluation and review technique (PERT) to estimate duration how many hours should the project manager plan to schedule the task taking into account all the positive and negative risk factors?

Options

  • A4 hours
  • B5 hours
  • C6 hours
  • D12 hours

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#PERT#Duration Estimation#Three-Point Estimation#Quantitative Risk Analysis
Full PMI-RMP PracticeBrowse All PMI-RMP Questions