nerdexam
PMI

PMI-RMP · Question #622

After completing the risk register, many team members feel there is a lack of time prioritization for one of the identified risks What are the team members referring to?

The correct answer is C. Risk urgency. Risk urgency refers to how soon a risk needs to be addressed - it captures the time-sensitivity of a risk response. If team members feel that time prioritization is lacking for a particular risk, they are pointing to a missing or inadequate urgency rating in the risk register…

Perform Targeted Risk Analysis

Question

After completing the risk register, many team members feel there is a lack of time prioritization for one of the identified risks What are the team members referring to?

Options

  • ARisk trigger
  • BRisk escalation
  • CRisk urgency
  • DRisk time impact

How the community answered

(33 responses)
  • A
    3% (1)
  • B
    6% (2)
  • C
    91% (30)

Explanation

Risk urgency refers to how soon a risk needs to be addressed - it captures the time-sensitivity of a risk response. If team members feel that time prioritization is lacking for a particular risk, they are pointing to a missing or inadequate urgency rating in the risk register (C). Risk urgency is distinct from risk impact or probability; it specifically addresses when action must be taken. A risk trigger (A) is an event indicating a risk is about to occur. Risk escalation (B) refers to elevating a risk to a higher authority. Risk time impact (D) refers to how the risk affects the project schedule, not when it must be addressed.

Topics

#Risk Urgency#Risk Prioritization#Qualitative Risk Analysis#Risk Register

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice