PMI-RMP · Question #609
A risk manager has been assigned to a new project and learns that stakeholders and project team members are spread across multiple time zones. Furthermore, many project team members have not worked to
The correct answer is D. Work with the project manager to develop a start-up workshop and colocate the team if permitted.. When team members are geographically dispersed and have not worked together, the most effective risk planning tool is a start-up (kickoff) workshop, which establishes relationships, shared understanding of goals, and team norms early. Colocation, when feasible, further reduces co
Question
A risk manager has been assigned to a new project and learns that stakeholders and project team members are spread across multiple time zones. Furthermore, many project team members have not worked together in the past. These items are identified as potential risks and added to the risk register. How should the risk manager improve collaboration during risk planning?
Options
- AGather risk information from all parties and compile all submissions into a strength, weaknesses,
- BCreate a repository for project documents and related artifacts that can be accessed by all parties.
- CCommunicate program metrics to all parties and create a scorecard to measure the effectiveness.
- DWork with the project manager to develop a start-up workshop and colocate the team if permitted.
How the community answered
(18 responses)- A6% (1)
- B6% (1)
- C17% (3)
- D72% (13)
Explanation
When team members are geographically dispersed and have not worked together, the most effective risk planning tool is a start-up (kickoff) workshop, which establishes relationships, shared understanding of goals, and team norms early. Colocation, when feasible, further reduces collaboration barriers. Option A (SWOT from gathered info) is a risk identification technique, not a collaboration improvement strategy. Option B (a shared document repository) supports collaboration passively but does not build the interpersonal relationships needed for effective risk discussion. Option C (program metrics and scorecards) is a monitoring activity, not a planning collaboration strategy. A start-up workshop directly addresses both the distributed team and unfamiliarity risks simultaneously.
Topics
Community Discussion
No community discussion yet for this question.