PMI-RMP · Question #599
A critical piece of equipment broke during a project execution phase. The risk manager notices this risk in the risk register, and the response is to rent equipment until the critical piece is repaire
The correct answer is C. Mitigate. Mitigation is a risk response strategy that reduces the probability or impact of a threat. Renting replacement equipment reduces the impact of the broken equipment risk by ensuring the project can continue operating - it does not eliminate the risk but lessens its effect on the p
Question
A critical piece of equipment broke during a project execution phase. The risk manager notices this risk in the risk register, and the response is to rent equipment until the critical piece is repaired. What type of risk response is this?
Options
- ATransfer
- BAccept
- CMitigate
- DAvoid
How the community answered
(22 responses)- A5% (1)
- B14% (3)
- C73% (16)
- D9% (2)
Explanation
Mitigation is a risk response strategy that reduces the probability or impact of a threat. Renting replacement equipment reduces the impact of the broken equipment risk by ensuring the project can continue operating - it does not eliminate the risk but lessens its effect on the project. Transfer (A) would shift the financial or operational consequence to a third party, such as through insurance or a vendor contract. Avoid (D) would eliminate the risk entirely, such as by redesigning the work to not need that equipment. Accept (B) would mean acknowledging the risk and taking no proactive steps. Because the team is actively reducing the negative impact through a contingency action, this is mitigation.
Topics
Community Discussion
No community discussion yet for this question.