nerdexam
PMIPMI

PMI-RMP · Question #598

PMI-RMP Question #598: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #598. The question stem and answer options stay visible for context.

Risk Process Facilitation

Question

A risk manager has been assigned to an upcoming project. A senior risk manager within the organization recently completed a similar project and has provided a lessons learned document to aid planning efforts for the upcoming project. Upon reviewing the document, the risk manager discovers that the completed project was delivered several months behind schedule and several thousands of dollars over budget. The root cause was determined to be an unforeseen risk trigger that caused several items to be reworked, creating cascading schedule delays and depleting management reserves. What should the risk manager do to mitigate the chance of the same issues reoccurring?

Options

  • AEnsure that all project stakeholders have a copy of and understand the project's risk management
  • BIncrease the management reserves and inform stakeholders of what is available to cover any
  • CDistribute the lessons learned document to stakeholders knowing that the likelihood of
  • DDocument the known risk triggers as the identified cost and schedule risks in the risk register.

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Lessons Learned#Risk Identification#Risk Register#Risk Triggers
Full PMI-RMP PracticeBrowse All PMI-RMP Questions