PMI-RMP · Question #600
In a highly dynamic project environment, the project manager is known to have project risks as a permanent agenda item in their periodic project progress meetings. How will this help improve the proje
The correct answer is A. By helping to monitor variances and trends frequently throughout the project C. By helping the lessons learned from previous risks to be efficiently utilized E. By helping update the risk register and close out expired risks. Making project risks a standing agenda item in periodic progress meetings improves risk management in three key ways: (A) It enables frequent monitoring of risk variances and trends, allowing early detection of changes in risk exposure throughout the project lifecycle. (C) It pro
Question
In a highly dynamic project environment, the project manager is known to have project risks as a permanent agenda item in their periodic project progress meetings. How will this help improve the project's risk management activities? (Choose 3)
Options
- ABy helping to monitor variances and trends frequently throughout the project
- BBy helping to determine the overall project risks
- CBy helping the lessons learned from previous risks to be efficiently utilized
- DBy helping to update the project scope statement document
- EBy helping update the risk register and close out expired risks
How the community answered
(29 responses)- A72% (21)
- B21% (6)
- D7% (2)
Explanation
Making project risks a standing agenda item in periodic progress meetings improves risk management in three key ways: (A) It enables frequent monitoring of risk variances and trends, allowing early detection of changes in risk exposure throughout the project lifecycle. (C) It provides a regular forum to discuss and apply lessons learned from risks that have already occurred or been resolved, improving team response over time. (E) It ensures the risk register is continuously updated - new risks are added, probability/impact ratings are revised, and expired or resolved risks are formally closed. Option (B) is incorrect because determining overall project risk requires specific quantitative/qualitative analysis techniques, not just meeting discussions. Option (D) is incorrect because scope statement updates are driven by the change control process, not risk meetings.
Topics
Community Discussion
No community discussion yet for this question.