PMI-RMP · Question #594
PMI-RMP Question #594: Real Exam Question with Answer & Explanation
The correct answer is A: Close and communicate the results of the risk response actions.. After verifying the effectiveness of the risk responses, the next step is to close out the risk response actions and communicate the results to relevant stakeholders. This ensures that the project team and stakeholders are aware of how risks have been managed and that any lessons
Question
As a project approached completion, a risk manager conducted a risk response audit and verified the effectiveness of risk responses. What should the risk manager do next?
Options
- AClose and communicate the results of the risk response actions.
- BRun a workshop to analyze the effectiveness of the risk plan.
- CConduct a risk reserve analysis and document the results.
- DVerify that all risk response actions have been documented.
Explanation
After verifying the effectiveness of the risk responses, the next step is to close out the risk response actions and communicate the results to relevant stakeholders. This ensures that the project team and stakeholders are aware of how risks have been managed and that any lessons learned can be applied to future projects. This aligns with PMI's emphasis on communication and documentation in risk management to ensure transparency and continuous improvement.