nerdexam
PMIPMI

PMI-RMP · Question #593

PMI-RMP Question #593: Real Exam Question with Answer & Explanation

The correct answer is A: Document the risk in the risk register for analysis.. If a risk requires external help and the contracting process is long, it is prudent to start the process immediately to avoid delays. This proactive approach ensures that the necessary resources will be available when needed. According to PMI guidelines, early action to address r

Risk Process Facilitation

Question

A project team is concerned about a risk which, if occurs, might add additional complexity to their work. The team will need help from an external vendor, but the contracting process is long. What should the risk manager do in this case?

Options

  • ADocument the risk in the risk register for analysis.
  • BDocument the detailed risk consequences,
  • CImmediately start the contracting process.
  • DProceed with the quantitative risk analysis.

Explanation

If a risk requires external help and the contracting process is long, it is prudent to start the process immediately to avoid delays. This proactive approach ensures that the necessary resources will be available when needed. According to PMI guidelines, early action to address risk is essential, especially when external dependencies are involved. Documenting the risk in the risk register or analyzing it further can be done concurrently, but starting the contracting process mitigates the risk of delay.

Topics

#Risk Identification#Risk Register#Risk Management Process#Documentation

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions