nerdexam
PMI

PMI-RMP · Question #593

A project team is concerned about a risk which, if occurs, might add additional complexity to their work. The team will need help from an external vendor, but the contracting process is long. What…

The correct answer is A. Document the risk in the risk register for analysis. When a risk is identified, the first formal step in the risk management process is to document it in the risk register. The risk register is the central repository for all identified risks and serves as the foundation for subsequent analysis and response planning. Starting the…

Risk Process Facilitation

Question

A project team is concerned about a risk which, if occurs, might add additional complexity to their work. The team will need help from an external vendor, but the contracting process is long. What should the risk manager do in this case?

Options

  • ADocument the risk in the risk register for analysis.
  • BDocument the detailed risk consequences,
  • CImmediately start the contracting process.
  • DProceed with the quantitative risk analysis.

How the community answered

(21 responses)
  • A
    90% (19)
  • B
    5% (1)
  • C
    5% (1)

Explanation

When a risk is identified, the first formal step in the risk management process is to document it in the risk register. The risk register is the central repository for all identified risks and serves as the foundation for subsequent analysis and response planning. Starting the contracting process immediately (C) would be premature and could waste resources before the risk is properly analyzed. Documenting detailed consequences (B) and performing quantitative analysis (D) are later steps that depend on the risk first being formally recorded. By logging the risk first, the team can then analyze it, plan a timely response - including initiating the lengthy contracting process if the risk analysis warrants it - without skipping critical steps.

Topics

#Risk Identification#Risk Register#Risk Management Process#Documentation

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice