nerdexam
PMIPMI

PMI-RMP · Question #576

PMI-RMP Question #576: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #576. The question stem and answer options stay visible for context.

Perform Targeted Risk Analysis

Question

Stakeholder holiday schedules and availability of raw materials were two risks initially identified in a manufacturing project. The risk manager now notices that both risks are not quite as originally described and might require a plan change. What should the risk manager do next?

Options

  • AConsult with the project manager to agree that these risks should be removed from the risk
  • BKeep the risks in the risk register and continue to follow up until the change actually takes place.
  • CIdentify workarounds that can be implemented whether or not the change takes place.
  • DRevisit the project the assumptions and constraints to potentially update the risk impact and

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk re-assessment#Risk analysis update#Assumptions and constraints#Risk characteristics
Full PMI-RMP PracticeBrowse All PMI-RMP Questions