nerdexam
PMIPMI

PMI-RMP · Question #575

PMI-RMP Question #575: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #575. The question stem and answer options stay visible for context.

Risk Monitoring and Reporting

Question

A project manager of an IT company is assigned to a project whose schedule may be delayed due to a lack of resources to conclude the backlog activities. The project manager decides to hire additional developers to reduce the project's technical debt and meet the project deadline. What should the risk manager advise the project manager to do to address this situation?

Options

  • AImmediately hire as soon as the project begins to fall behind schedule.
  • BHire as soon as the project metrics trigger a risk response.
  • COnly hire when it is economically feasible to do so.
  • DOnly hire if risk response is escalated and approved by the stakeholders.

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk response implementation#Risk monitoring#Trigger conditions#Planned risk responses
Full PMI-RMP PracticeBrowse All PMI-RMP Questions