nerdexam
PMI

PMI-RMP · Question #575

A project manager of an IT company is assigned to a project whose schedule may be delayed due to a lack of resources to conclude the backlog activities. The project manager decides to hire additional

The correct answer is B. Hire as soon as the project metrics trigger a risk response.. Effective risk management requires predefined triggers-specific measurable thresholds (metrics) established during risk planning that signal when a risk response should be activated. Hiring when metrics trigger the response ensures objectivity, timeliness, and alignment with the

Risk Monitoring and Reporting

Question

A project manager of an IT company is assigned to a project whose schedule may be delayed due to a lack of resources to conclude the backlog activities. The project manager decides to hire additional developers to reduce the project's technical debt and meet the project deadline. What should the risk manager advise the project manager to do to address this situation?

Options

  • AImmediately hire as soon as the project begins to fall behind schedule.
  • BHire as soon as the project metrics trigger a risk response.
  • COnly hire when it is economically feasible to do so.
  • DOnly hire if risk response is escalated and approved by the stakeholders.

How the community answered

(13 responses)
  • A
    8% (1)
  • B
    77% (10)
  • D
    15% (2)

Explanation

Effective risk management requires predefined triggers-specific measurable thresholds (metrics) established during risk planning that signal when a risk response should be activated. Hiring when metrics trigger the response ensures objectivity, timeliness, and alignment with the approved risk management plan. Hiring immediately when the project falls behind (A) is reactive and lacks the precision of trigger-based responses. Waiting only until it is economically feasible (C) subordinates schedule risk to cost considerations and may result in acting too late. Escalating for stakeholder approval each time (D) creates unnecessary delays and is reserved for risks outside the team's authority.

Topics

#Risk response implementation#Risk monitoring#Trigger conditions#Planned risk responses

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice