The correct answer is D: Perform a risk urgency assessment.. When a risk triggers several other risks that need a quick response, performing a risk urgency assessment is the appropriate course of action. This assessment helps determine how soon a response is required for each risk, considering their potential impact on the project. The PMI
Question
During a project progress meeting, a project team member is concerned that one of the risks has triggered several other low-level risks. These risks should be responded to quickly or there will be severe consequences for the project deliverables. What should the risk manager do?
Options
- AUpdate the watchlist.
- BInitiate a risk response when these risks occur.
- CAddress only the high-priority risk.
- DPerform a risk urgency assessment.
Explanation
When a risk triggers several other risks that need a quick response, performing a risk urgency assessment is the appropriate course of action. This assessment helps determine how soon a response is required for each risk, considering their potential impact on the project. The PMI guidelines emphasize the importance of urgency in prioritizing risk responses, particularly when the consequences could significantly affect project deliverables if not addressed promptly.