Perform Targeted Risk Analysis
Question
A large, land-based infrastructure project has begun. The project makes assumptions about the site conditions and has economic, technical, and environmental constraints What should the project manager do next to determine risk impact of assumptions and constraints?
Options
- AAdd all assumptions and constraints to the risk register.
- BAdd the risk impact of the assumptions in the risk register.
- CAdd the assumptions and constraints to the assumption log.
- DAdd the assumptions and constraints in the project charter.
Unlock PMI-RMP to see the answer
You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Assumptions Management#Constraints Management#Assumption Log#Risk Identification Inputs