nerdexam
PMIPMI

PMI-RMP · Question #500

PMI-RMP Question #500: Real Exam Question with Answer & Explanation

The correct answer is B: Reassess risks with a new assumptions and constraints analysis.. The project manager should reassess risks by conducting a new assumptions and constraints analysis. This will help identify any previously overlooked risks and ensure that the risk register is comprehensive and up-to-date.

Perform Targeted Risk Analysis

Question

A project manager was informed that the testing of the latest component in the project's software update release was not successful. As a result, 1he delivery timelines for the software release wifi be delayed, The project manager did not previously capture this as a risk to the project. What should the project manager do next to avoid similar risks?

Options

  • AAdd contingencies to other tasks to mitigate similar risks.
  • BReassess risks with a new assumptions and constraints analysis.
  • CReview the risk response plan looking for lessons learned.
  • DLog the event in the issue log and update the project management plan.

Explanation

The project manager should reassess risks by conducting a new assumptions and constraints analysis. This will help identify any previously overlooked risks and ensure that the risk register is comprehensive and up-to-date.

Topics

#Risk identification#Assumptions and constraints analysis#Risk reassessment#Proactive risk management

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions