nerdexam
PMI

PMI-RMP · Question #500

A project manager was informed that the testing of the latest component in the project's software update release was not successful. As a result, 1he delivery timelines for the software release wifi b

The correct answer is B. Reassess risks with a new assumptions and constraints analysis.. Because the failed testing risk was never captured, it was likely rooted in an unchallenged assumption or an unexamined constraint-for example, assuming the component would pass testing. Reassessing risks using an assumptions and constraints analysis directly targets the root cau

Perform Targeted Risk Analysis

Question

A project manager was informed that the testing of the latest component in the project's software update release was not successful. As a result, 1he delivery timelines for the software release wifi be delayed, The project manager did not previously capture this as a risk to the project. What should the project manager do next to avoid similar risks?

Options

  • AAdd contingencies to other tasks to mitigate similar risks.
  • BReassess risks with a new assumptions and constraints analysis.
  • CReview the risk response plan looking for lessons learned.
  • DLog the event in the issue log and update the project management plan.

How the community answered

(16 responses)
  • A
    6% (1)
  • B
    75% (12)
  • C
    13% (2)
  • D
    6% (1)

Explanation

Because the failed testing risk was never captured, it was likely rooted in an unchallenged assumption or an unexamined constraint-for example, assuming the component would pass testing. Reassessing risks using an assumptions and constraints analysis directly targets the root cause: identifying hidden assumptions that, if wrong, could generate similar unforeseen risks. Option A (adding contingency) treats the symptom, not the cause. Option C (reviewing the risk response plan) is not useful because no response plan existed for this risk. Option D (logging in the issue log) is appropriate for managing the current problem but does not help prevent similar risks in the future.

Topics

#Risk identification#Assumptions and constraints analysis#Risk reassessment#Proactive risk management

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice