PMI-RMP · Question #500
PMI-RMP Question #500: Real Exam Question with Answer & Explanation
The correct answer is B: Reassess risks with a new assumptions and constraints analysis.. The project manager should reassess risks by conducting a new assumptions and constraints analysis. This will help identify any previously overlooked risks and ensure that the risk register is comprehensive and up-to-date.
Question
A project manager was informed that the testing of the latest component in the project's software update release was not successful. As a result, 1he delivery timelines for the software release wifi be delayed, The project manager did not previously capture this as a risk to the project. What should the project manager do next to avoid similar risks?
Options
- AAdd contingencies to other tasks to mitigate similar risks.
- BReassess risks with a new assumptions and constraints analysis.
- CReview the risk response plan looking for lessons learned.
- DLog the event in the issue log and update the project management plan.
Explanation
The project manager should reassess risks by conducting a new assumptions and constraints analysis. This will help identify any previously overlooked risks and ensure that the risk register is comprehensive and up-to-date.
Topics
Community Discussion
No community discussion yet for this question.