nerdexam
PMIPMI

PMI-RMP · Question #499

PMI-RMP Question #499: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #499. The question stem and answer options stay visible for context.

Risk Strategy and Planning

Question

A risk manager manages risks in a construction project. A stakeholder mentions that if there is less than a 50% chance of rain, construction should continue. Another stakeholder says that if there is less than a 60% chance of rain, construction should continue. What should the risk manager do next to find out the correct limit?

Options

  • AReview the agreed-upon risk tolerance
  • BPerform a sensitivity analysis of the risk
  • CFind out the stakeholders' risk appetite
  • DUse industry standard risk thresholds

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk tolerance#Risk thresholds#Stakeholder alignment#Risk planning
Full PMI-RMP PracticeBrowse All PMI-RMP Questions