nerdexam
PMI

PMI-RMP · Question #499

A risk manager manages risks in a construction project. A stakeholder mentions that if there is less than a 50% chance of rain, construction should continue. Another stakeholder says that if there is

The correct answer is A. Review the agreed-upon risk tolerance. When two stakeholders disagree about acceptable probability thresholds for continuing work, the risk manager should refer to the agreed-upon, documented risk tolerance-not to either individual's preference. Risk tolerance is the quantified, pre-agreed boundary of acceptable risk

Risk Strategy and Planning

Question

A risk manager manages risks in a construction project. A stakeholder mentions that if there is less than a 50% chance of rain, construction should continue. Another stakeholder says that if there is less than a 60% chance of rain, construction should continue. What should the risk manager do next to find out the correct limit?

Options

  • AReview the agreed-upon risk tolerance
  • BPerform a sensitivity analysis of the risk
  • CFind out the stakeholders' risk appetite
  • DUse industry standard risk thresholds

How the community answered

(16 responses)
  • A
    75% (12)
  • B
    13% (2)
  • C
    6% (1)
  • D
    6% (1)

Explanation

When two stakeholders disagree about acceptable probability thresholds for continuing work, the risk manager should refer to the agreed-upon, documented risk tolerance-not to either individual's preference. Risk tolerance is the quantified, pre-agreed boundary of acceptable risk variation, and it is recorded in the risk management plan. It resolves exactly this kind of stakeholder disagreement by providing an objective, project-level standard. Sensitivity analysis (B) measures risk impact, not thresholds. Risk appetite (C) is a broader strategic concept about willingness to pursue risk for reward, not a specific operational cutoff. Industry standards (D) are a fallback, not a substitute for project-specific documented agreements.

Topics

#Risk tolerance#Risk thresholds#Stakeholder alignment#Risk planning

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice