PMI-RMP · Question #491
PMI-RMP Question #491: Real Exam Question with Answer & Explanation
Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #491. The question stem and answer options stay visible for context.
Question
A project's design has been completed and approved on time. The construction subcontractor should be mobilizing to start construction but does not have the necessary materials in place, causing a delaying in the project. The risk register only contains risks for the design phase of the project. What should the project manager have done differently?
Options
- AExecuted the Monte Carlo sensitivity analysis prior to mobilization
- BAdded generic construction risks to the risk register before construction began
- CReviewed the assumptions/exclusions register in the project charter
- DPerformed risk identification exercises for the full lifecycle of the project
Unlock PMI-RMP to see the answer
You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.