The correct answer is B: Defining how risk management will be executed throughout the project.. The expected outcome of developing the risk management plan is to define how risk management activities will be executed throughout the project. This includes the processes, tools, and techniques that will be used to identify, assess, and manage risks. The risk management plan is

Risk Strategy and Planning

Question

A project manager has just been assigned to a new project. The project manager has been tasked by the project sponsor to ensure the project risks are closely managed. The project manager starts with developing the risk management plan. What is the expected outcome of developing the risk management plan?

Options

  • ABeing able to monitor and control risks throughout the project.
  • BDefining how risk management will be executed throughout the project.
  • CDocumenting the communication strategy for risks throughout the project.
  • DHaving the ability to identify risks throughout the project.

Explanation

The expected outcome of developing the risk management plan is to define how risk management activities will be executed throughout the project. This includes the processes, tools, and techniques that will be used to identify, assess, and manage risks. The risk management plan is a document that describes how risk management activities will be structured and performed throughout the project. It provides guidance on how to identify, analyze, respond, monitor, and control risks, as well as how to communicate, document, and report them. The risk management plan also defines the roles and responsibilities of the project team and stakeholders in risk management, the risk categories and breakdown structure, the risk thresholds and appetite, the risk management tools and techniques, and the risk management budget and schedule. The risk management plan is an output of the plan risk management process, which is the first process in the project risk management knowledge area. Developing the risk management plan is essential for ensuring that the project risks are closely managed and aligned with the project objectives and stakeholder expectations.

Topics

#Risk Management Plan#Risk Planning#Defining Risk Approach