PMI-RMP · Question #484
PMI-RMP Question #484: Real Exam Question with Answer & Explanation
The correct answer is A: Put the risk on the watch list.. Since the probability and impact the risk are both low, it is appropriate to put the risk on the watch list. This allows the risk manager to monitor the risk without expending significant resources on it. A watch list is a list of low-priority risks that are not actively managed,
Question
A risk manager is managing risks in a project. During the initial stages of project execution, a new risk is identified. There is a very small chance that this risk will occur and even if it occurs, the impact would be low. What should the risk manager do with this risk?
Options
- APut the risk on the watch list.
- BSeek guidance from subject matter experts (SMEs).
- CIgnore this risk as it is not critical.
- DInform the stakeholders about this risk.
Explanation
Since the probability and impact the risk are both low, it is appropriate to put the risk on the watch list. This allows the risk manager to monitor the risk without expending significant resources on it. A watch list is a list of low-priority risks that are not actively managed, but are monitored for changes. A watch list can help the risk manager to keep track of the risks that have low probability and low impact, and to reassess them periodically. Putting the risk on the watch list is the most appropriate action for the risk manager, as it allows him or her to document the risk and review it later. Seeking guidance from SMEs, ignoring the risk, or informing the stakeholders are not necessary actions for a low-priority risk, as they would consume time and resources that could be better spent on more critical risks.
Topics
Community Discussion
No community discussion yet for this question.