A project manager identified a risk of communication issues with the client which may impact the project schedule. A member of (he sales team advises that this client prefers face-to- face conversatio
The correct answer is D. Meet the client and plan tor critical milestone meetings.. The risk identified is communication issues with the client that could impact the project schedule. The sales team reveals the client prefers face-to-face interaction. To 'avoid' this risk means eliminating the cause entirely. By meeting the client and planning critical milestone
Question
A project manager identified a risk of communication issues with the client which may impact the project schedule. A member of (he sales team advises that this client prefers face-to- face conversations. What should the project manager do to avoid this risk?
Options
- ARecord this risk and the clients preference in the risk register.
- BAsk the sales person to lead the communication with the client
- CCall the client and advise that online communication is easier and faster.
- DMeet the client and plan tor critical milestone meetings.
How the community answered
(31 responses)- A6% (2)
- B10% (3)
- C3% (1)
- D81% (25)
Explanation
The risk identified is communication issues with the client that could impact the project schedule. The sales team reveals the client prefers face-to-face interaction. To 'avoid' this risk means eliminating the cause entirely. By meeting the client and planning critical milestone meetings in person, the project manager directly removes the communication friction, satisfying the client's preference. This is a risk avoidance strategy. Option A only documents the risk without resolving it. Options B and C do not address the root cause effectively and could worsen the relationship.