nerdexam
PMIPMI

PMI-RMP · Question #486

PMI-RMP Question #486: Real Exam Question with Answer & Explanation

The correct answer is A: Lessons learned. When closing risks as part of the closing process, it is important to update the lessons learned document. This document captures the knowledge and experience gained during the project and can be valuable for future projects. Lessons learned is a document that captures the knowle

Risk Monitoring and Reporting

Question

A complex project that had hundreds of risks is almost done. The project manager is closing the risks as part of the closing process. One team member mentions that there are important documents to be updated. Which document will need to be updated?

Options

  • ALessons learned
  • BContingency register
  • CRisk register
  • DIssue log

Explanation

When closing risks as part of the closing process, it is important to update the lessons learned document. This document captures the knowledge and experience gained during the project and can be valuable for future projects. Lessons learned is a document that captures the knowledge gained from the project and can help improve the performance of future projects. It is one of the outputs of the project closure process and should include information on the project risks, issues, and responses. Lessons learned can help identify the best practices and lessons to be applied or avoided in similar projects. Updating the lessons learned document is an important part of closing the risks as it can provide valuable insights for risk management.

Topics

#Lessons Learned#Project Closure#Risk Management Process#Organizational Process Assets

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions