PMI-RMP · Question #486
A complex project that had hundreds of risks is almost done. The project manager is closing the risks as part of the closing process. One team member mentions that there are important documents to be
The correct answer is A. Lessons learned. During project closure, the lessons learned register (also called lessons learned documentation) is one of the most important documents to update. It captures what went well, what went poorly, and what the team would do differently-including how hundreds of risks were identified,
Question
A complex project that had hundreds of risks is almost done. The project manager is closing the risks as part of the closing process. One team member mentions that there are important documents to be updated. Which document will need to be updated?
Options
- ALessons learned
- BContingency register
- CRisk register
- DIssue log
How the community answered
(36 responses)- A81% (29)
- B6% (2)
- C11% (4)
- D3% (1)
Explanation
During project closure, the lessons learned register (also called lessons learned documentation) is one of the most important documents to update. It captures what went well, what went poorly, and what the team would do differently-including how hundreds of risks were identified, managed, and closed. This document becomes organizational process assets for future projects. The risk register (C) and issue log (D) are operational documents that are closed out, not updated with retrospective insights. A 'contingency register' is not a standard PMI artifact.