PMI-RMP · Question #466
The project manager is reviewing the lessons learned from a previous similar project. The previous project was delayed due to the delay in delivery of a gas turbine generator (GTG). Construction of th
The correct answer is C. Review and update the project schedule.. Because the lessons learned clearly document a specific, proven risk (late GTG delivery causing shutdown), the project manager already has sufficient information to take immediate proactive action. Reviewing and updating the project schedule (C) is the first priority because it a
Question
The project manager is reviewing the lessons learned from a previous similar project. The previous project was delayed due to the delay in delivery of a gas turbine generator (GTG). Construction of the previous project had to be shut down unexpectedly to wait for the late delivery of the GTG. What should the project manager do first?
Options
- AInclude the risk in the register and communicate with the stakeholders.
- BCommunicate with the client to provide the previous shutdown plan.
- CReview and update the project schedule.
- DInterview the other project manager to learn more details.
How the community answered
(31 responses)- A6% (2)
- B3% (1)
- C77% (24)
- D13% (4)
Explanation
Because the lessons learned clearly document a specific, proven risk (late GTG delivery causing shutdown), the project manager already has sufficient information to take immediate proactive action. Reviewing and updating the project schedule (C) is the first priority because it allows the PM to identify where the GTG delivery sits in the schedule, assess whether current lead times are adequate, add buffer or adjust sequencing to prevent a repeat shutdown, and understand the current exposure. This directly protects the project. Option A (adding to the risk register and communicating) is a valid next step but should follow the schedule review. Option B (communicating about a shutdown plan) is reactive and premature. Option D (interviewing the other PM) might add nuance but the lesson learned document already provides the critical fact; additional discovery can occur in parallel but is not the first action.