nerdexam
PMIPMI

PMI-RMP · Question #465

PMI-RMP Question #465: Real Exam Question with Answer & Explanation

The correct answer is A: Perform a qualitative risk analysis and update the results.. The risk manager should perform a quantitative risk analysis to determine the potential impact of risks on the project's completion date. This will help in providing a more accurate project completion date to the customer, considering the risks and their potential effects on the

Perform Targeted Risk Analysis

Question

Towards the end of definitive design, project costs have increased to the point where it will be classified as a capital asset project. The customer has expressed they want one final total project completion date and will afford no extensions after it is established. How should the risk manager proceed?

Options

  • APerform a qualitative risk analysis and update the results.
  • BUpdate the assumptions/exclusions register with the new information.
  • CUpdate the risk register and prepare for the Monte Carlo analysis.
  • DPerform a quantitative risk analysis and update the results.

Explanation

The risk manager should perform a quantitative risk analysis to determine the potential impact of risks on the project's completion date. This will help in providing a more accurate project completion date to the customer, considering the risks and their potential effects on the project one of the tasks in the domain of Risk Analysis is to perform quantitative risk analysis using techniques such as Monte Carlo simul-ation, decision tree analysis, sensitivity analysis, etc., to quantify the possible outcomes for the project and their probabilities, and to evaluate the cost and schedule impacts of risks. In this scenario, the risk manager should perform a quantitative risk analysis and update the results, because the project costs have increased significantly and the customer has imposed a strict deadline for the project completion. A quantitative risk analysis will help the risk manager to estimate the probability of meeting the project objectives, such as cost and schedule, and to determine the appropriate contingency reserves for the project. A quantitative risk analysis will also provide more accurate and reliable information for the customer and the project team, and will support the risk response planning process.

Topics

#Qualitative Risk Analysis#Risk Assessment#Project Constraints#Risk Management Process

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions