nerdexam
PMI

PMI-RMP · Question #465

Towards the end of definitive design, project costs have increased to the point where it will be classified as a capital asset project. The customer has expressed they want one final total project com

Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #465. The question stem and answer options stay visible for context.

Perform Targeted Risk Analysis

Question

Towards the end of definitive design, project costs have increased to the point where it will be classified as a capital asset project. The customer has expressed they want one final total project completion date and will afford no extensions after it is established. How should the risk manager proceed?

Options

  • APerform a qualitative risk analysis and update the results.
  • BUpdate the assumptions/exclusions register with the new information.
  • CUpdate the risk register and prepare for the Monte Carlo analysis.
  • DPerform a quantitative risk analysis and update the results.

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Qualitative Risk Analysis#Risk Assessment#Project Constraints#Risk Management Process
Full PMI-RMP Practice