PMI-RMP · Question #464
PMI-RMP Question #464: Real Exam Question with Answer & Explanation
The correct answer is D: Apply an iterative approach to risk identification.. The project manager should apply an iterative approach to risk identification, which involves continuous risk identification throughout the project lifecycle. This will help to identify and address new risks that may arise during the project. Risk identification is the process of
Question
Multiple new risks have come up on a project that were not included on the risk register. The project manager met with the team to explain that risk management is critical for the success of the project, and risk identification is key. What should the project manager do next?
Options
- AReview assumptions and constraints around risks.
- BDevelop the risk response plans for identified risks.
- CDetermine the likelihood and impact of the risks.
- DApply an iterative approach to risk identification.
Explanation
The project manager should apply an iterative approach to risk identification, which involves continuous risk identification throughout the project lifecycle. This will help to identify and address new risks that may arise during the project. Risk identification is the process of determining which risks may affect the project and documenting their characteristics. It is an iterative process because new risks may evolve or become known only as the project progresses through its life cycle. There are many techniques available for risk identification and assessment, such as brainstorming, interviews, checklists, SWOT analysis, cause and effect diagrams, etc. The project manager should apply an iterative approach to risk identification to ensure that all relevant risks are captured and updated throughout the project. The project manager should also involve the project team and other stakeholders in the risk identification process to obtain their input and perspectives.
Topics
Community Discussion
No community discussion yet for this question.