PMI-RMP · Question #463
A certain risk is identified for a major project, and the risk response is planned. However, the analysis reveals a high probability for a secondary risk which will be tolerated based on the organizat
Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #463. The question stem and answer options stay visible for context.
Question
A certain risk is identified for a major project, and the risk response is planned. However, the analysis reveals a high probability for a secondary risk which will be tolerated based on the organization's risk thresholds. The secondary risk is subsequently registered. During project execution, the primary risk occurs, the planned action is taken, and the secondary risk emerges What two actions should the risk owner take? (Choose two.)
Options
- AImplement the secondary risk response and update the project documents.
- BConduct meeting with all stakeholder to agree on post impact solutions.
- CSet the corresponding trigger conditions to the secondary risk.
- DEngage the project manager to authorize the secondary risk's response.
- EUpdate and communicate assessments of the secondary risk's impact.
Unlock PMI-RMP to see the answer
You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.