PMIPMI
PMI-RMP · Question #454
PMI-RMP Question #454: Real Exam Question with Answer & Explanation
Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #454. The question stem and answer options stay visible for context.
Risk Strategy and Planning
Question
The project director and project manager have met with the board and determined that the project has depleted the entire contingency reserve and has started eroding the profit margin. The project manager would like the risk manager to take full advantage of opportunities. Which response should the risk manager take?
Options
- AMitigate
- BAccept
- CTransfer
- DExploit
Unlock PMI-RMP to see the answer
You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Risk response strategies#Opportunity management#Exploit strategy