PMI-RMP · Question #453
A risk manager documents the causes in the risk register and needs to ensure the risk is adequately described. What is critical for the risk manager to consider when describing the causes?
The correct answer is C. The causes represent actual conditions. When describing the causes of a risk, it is critical for the risk manager to ensure that the causes represent actual conditions, as this will help in the accurate identification and assessment of the. According to the PMBOK?Guide, a risk is defined as "an uncertain event or…
Question
A risk manager documents the causes in the risk register and needs to ensure the risk is adequately described. What is critical for the risk manager to consider when describing the causes?
Options
- AEach cause has a degree of uncertainty
- BEach cause has well defined owner
- CThe causes represent actual conditions
- DThe causes must be validated by the risk owner
How the community answered
(22 responses)- A5% (1)
- C95% (21)
Explanation
When describing the causes of a risk, it is critical for the risk manager to ensure that the causes represent actual conditions, as this will help in the accurate identification and assessment of the. According to the PMBOK?Guide, a risk is defined as "an uncertain event or condition that, if it occurs, has a positive or negative effect on one or more project objectives" (page 720). A risk can be described by its causes, effects, and probability of occurrence. The causes are the factors or circumstances that give rise to the risk, and they should represent the actual conditions that exist or may exist in the project environment. The causes should not be based on assumptions, opinions, or speculations, but on facts, evidence, or data.
Topics