PMI-RMP · Question #290
Which of the following is an input to identify risk?
The correct answer is A. Organizational process assets. Organizational process assets are a key input to the Identify Risks process, providing historical data, lessons learned, and risk templates from previous projects.
Question
Which of the following is an input to identify risk?
Options
- AOrganizational process assets
- BScope management plan
- CCommunication management plan
- DExpert judgment
How the community answered
(27 responses)- A89% (24)
- C4% (1)
- D7% (2)
Why each option
Organizational process assets are a key input to the Identify Risks process, providing historical data, lessons learned, and risk templates from previous projects.
Organizational process assets include historical project files, lessons learned from previous projects, risk checklists, and risk statement templates - all of which directly inform risk identification by leveraging prior organizational experience and knowledge.
The scope management plan describes how the scope will be defined and managed; while scope documentation can inform risk identification, the scope management plan itself is not a primary input to Identify Risks.
The communication management plan governs how project communications are managed and is not listed as an input to the Identify Risks process.
Expert judgment is a tool and technique used within the Identify Risks process, not an input to it.
Concept tested: Inputs to the Identify Risks process