Which of the following is an input to identify risk?

The correct answer is A. Organizational process assets. Organizational process assets are a key input to the Identify Risks process, providing historical data, lessons learned, and risk templates from previous projects.

Risk Strategy and Planning

Question

Which of the following is an input to identify risk?

Options

  • AOrganizational process assets
  • BScope management plan
  • CCommunication management plan
  • DExpert judgment

How the community answered

(27 responses)
  • A
    89% (24)
  • C
    4% (1)
  • D
    7% (2)

Why each option

Organizational process assets are a key input to the Identify Risks process, providing historical data, lessons learned, and risk templates from previous projects.

AOrganizational process assetsCorrect

Organizational process assets include historical project files, lessons learned from previous projects, risk checklists, and risk statement templates - all of which directly inform risk identification by leveraging prior organizational experience and knowledge.

BScope management plan

The scope management plan describes how the scope will be defined and managed; while scope documentation can inform risk identification, the scope management plan itself is not a primary input to Identify Risks.

CCommunication management plan

The communication management plan governs how project communications are managed and is not listed as an input to the Identify Risks process.

DExpert judgment

Expert judgment is a tool and technique used within the Identify Risks process, not an input to it.

Concept tested: Inputs to the Identify Risks process

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok