The risk register contains which of the following?

The correct answer is A. Identified risks and potential responses. The risk register is the primary output of the Identify Risks process and contains identified risks along with potential responses and other risk details.

Risk Process Facilitation

Question

The risk register contains which of the following?

Options

  • AIdentified risks and potential responses
  • BIdentified risks and updates to scope baseline
  • CRisk management plan
  • DRisk related contract decisions

How the community answered

(27 responses)
  • A
    89% (24)
  • B
    7% (2)
  • C
    4% (1)

Why each option

The risk register is the primary output of the Identify Risks process and contains identified risks along with potential responses and other risk details.

AIdentified risks and potential responsesCorrect

The risk register documents identified risks along with their root causes, potential risk responses, risk owners, and other attributes. It is a living document updated as risks are analyzed and responses are planned, serving as the central repository for all risk information throughout the project.

BIdentified risks and updates to scope baseline

The risk register does not contain updates to the scope baseline - the scope baseline is a separate project document maintained through change control.

CRisk management plan

The risk management plan is a separate document that describes how risk management activities will be performed - it is an input to risk processes, not a component of the risk register.

DRisk related contract decisions

Risk-related contract decisions are documented in procurement documents and contracts, not in the risk register.

Concept tested: Risk register contents and purpose

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok