PMI-RMP · Question #279
PMI-RMP Question #279: Real Exam Question with Answer & Explanation
The correct answer is C: Risk reassessments are regularly scheduled; risk audits are performed as defined in the project's risk. Risk reassessment is an ongoing activity by the project team. Risks should be discussed at every status meeting. Risk audits are performed during the project life cycle to examine and document the effectiveness of risk responses. They are conducted at appropriate frequencies as d
Question
What is the primary difference between a risk audit and a risk reassessment?
Options
- AA risk reassessment is conducted at the completion of a major phase; audits are conducted after the
- BProject stakeholders conduct risk audits; management conducts reassessments.
- CRisk reassessments are regularly scheduled; risk audits are performed as defined in the project's risk
- DThere is no difference; they are virtually the same.
Explanation
Risk reassessment is an ongoing activity by the project team. Risks should be discussed at every status meeting. Risk audits are performed during the project life cycle to examine and document the effectiveness of risk responses. They are conducted at appropriate frequencies as defined in the risk management plan. [Monitoring and Controlling] PMI®, PMBOK® Guide, 2013, 351
Topics
Community Discussion
No community discussion yet for this question.