The primary advantage of using decision-tree analysis in project risk management is that it______________

The correct answer is B. Forces consideration of the probability of each outcome. As a graphical way to bring together information, decision-tree analysis quantifies the likelihood of failure and places a value on each decision. Usually applied to cost and time considerations, this form of risk analysis may be linked to a sensitivity analysis. [Planning]…

Perform Targeted Risk Analysis

Question

The primary advantage of using decision-tree analysis in project risk management is that it______________

Options

  • AConsiders the attitude of the decision maker toward risk
  • BForces consideration of the probability of each outcome
  • CHelps to identify and postulate risk scenarios for the project
  • DShows how risks can occur in combination

How the community answered

(57 responses)
  • A
    2% (1)
  • B
    93% (53)
  • C
    4% (2)
  • D
    2% (1)

Explanation

As a graphical way to bring together information, decision-tree analysis quantifies the likelihood of failure and places a value on each decision. Usually applied to cost and time considerations, this form of risk analysis may be linked to a sensitivity analysis. [Planning] PMI®, PMBOK® Guide, 2013, 339 Wide man 1992, C-2 and C-3