The purpose of a numeric scale in risk management is to______________

The correct answer is B. Assign a relative value to the impact on project objectives if the risk in question occurs. You can develop relative or numeric, well-defined scales using agreed-upon definitions by the stakeholders. When using a numeric scale, each level of impact has a specific number assigned to it. [Planning] PMI®, PMBOK® Guide, 2013, 331-332

Perform Targeted Risk Analysis

Question

The purpose of a numeric scale in risk management is to______________

Options

  • AAvoid high-impact risks
  • BAssign a relative value to the impact on project objectives if the risk in question occurs
  • CRank order risks in terms of very low, low, moderate, high, and very high
  • DTest project assumptions

How the community answered

(26 responses)
  • A
    4% (1)
  • B
    92% (24)
  • C
    4% (1)

Explanation

You can develop relative or numeric, well-defined scales using agreed-upon definitions by the stakeholders. When using a numeric scale, each level of impact has a specific number assigned to it. [Planning] PMI®, PMBOK® Guide, 2013, 331-332