The purpose of a numeric scale in risk management is to______________
The correct answer is B. Assign a relative value to the impact on project objectives if the risk in question occurs. You can develop relative or numeric, well-defined scales using agreed-upon definitions by the stakeholders. When using a numeric scale, each level of impact has a specific number assigned to it. [Planning] PMI®, PMBOK® Guide, 2013, 331-332
Perform Targeted Risk Analysis
Question
The purpose of a numeric scale in risk management is to______________
Options
- AAvoid high-impact risks
- BAssign a relative value to the impact on project objectives if the risk in question occurs
- CRank order risks in terms of very low, low, moderate, high, and very high
- DTest project assumptions
How the community answered
(26 responses)- A4% (1)
- B92% (24)
- C4% (1)
Explanation
You can develop relative or numeric, well-defined scales using agreed-upon definitions by the stakeholders. When using a numeric scale, each level of impact has a specific number assigned to it. [Planning] PMI®, PMBOK® Guide, 2013, 331-332
Topics
#Risk impact assessment#Numeric scales#Qualitative risk analysis