A workaround is______________
The correct answer is A. An unplanned response to a negative risk event. Used in control risks, a workaround is a response to a threat that has occurred for which a prior response had not been planned or was not effective. [Monitoring and Controlling] PMI®, PMBOK® Guide, 2013, 567
Risk Monitoring and Reporting
Question
A workaround is______________
Options
- AAn unplanned response to a negative risk event
- BA plan of action to follow when something unexpected occurs
- CA specific response to certain types of risk as described in the risk management plan
- DA proactive, planned method of responding to risks
How the community answered
(47 responses)- A87% (41)
- B2% (1)
- C9% (4)
- D2% (1)
Explanation
Used in control risks, a workaround is a response to a threat that has occurred for which a prior response had not been planned or was not effective. [Monitoring and Controlling] PMI®, PMBOK® Guide, 2013, 567