PMI-RMP · Question #274

You have heard recently that the client calls your progress reports the "Code of Hammurabi" because they seem to be written in hieroglyphics and are completely indecipherable to all but an antiquities

The correct answer is D. Engaging in communications planning. The communications management plan is prepared during plan communications management. The plan should include a description of the information to be distributed such as format, content, level of detail, as well as conventions and definitions to be used. [Planning] PMI®, PMBOK® Gu

Stakeholder Engagement

Question

You have heard recently that the client calls your progress reports the "Code of Hammurabi" because they seem to be written in hieroglyphics and are completely indecipherable to all but an antiquities scholar. This situation could have been avoided by______________

Options

  • AInforming the client at the start of the project about the types of reports they will receive
  • BUsing risk management techniques to identify client issues
  • CHiring an expert report writer to prepare standard reports
  • DEngaging in communications planning

How the community answered

(30 responses)
  • A
    10% (3)
  • B
    3% (1)
  • C
    3% (1)
  • D
    83% (25)

Explanation

The communications management plan is prepared during plan communications management. The plan should include a description of the information to be distributed such as format, content, level of detail, as well as conventions and definitions to be used. [Planning] PMI®, PMBOK® Guide, 2013, 296

Topics

#Communications planning#Stakeholder communication#Reporting clarity#Client engagement

Community Discussion

No community discussion yet for this question.