PMI-RMP · Question #248
John works as a project manager for ABD project. He and his team, are working on the following activities: - Relative ranking or priority list of project risks - Watchlists of low priority risk Trends
The correct answer is A. Perform Qualitative Risk Analysis. Perform Qualitative Risk Analysis is the process that produces the outputs described: a relative ranking or priority list of project risks (risks ranked by probability × impact), watchlists of low-priority risks (risks too low to actively manage but worth monitoring), and trends
Question
John works as a project manager for ABD project. He and his team, are working on the following activities:
- Relative ranking or priority list of project risks
- Watchlists of low priority risk
Trends in Qualitative Risk Analysis results On which of the following processes is John working on?
Options
- APerform Qualitative Risk Analysis
- BPlan Risk Management
- CPlan Risk Responses
- DPerform Quantitative Risk Analysis
How the community answered
(50 responses)- A90% (45)
- B2% (1)
- C4% (2)
- D4% (2)
Explanation
Perform Qualitative Risk Analysis is the process that produces the outputs described: a relative ranking or priority list of project risks (risks ranked by probability × impact), watchlists of low-priority risks (risks too low to actively manage but worth monitoring), and trends in qualitative risk analysis results (patterns emerging over time). Plan Risk Management (B) produces the Risk Management Plan, not risk rankings. Plan Risk Responses (C) produces risk response strategies. Perform Quantitative Risk Analysis (D) produces numerical probability distributions, sensitivity analyses, and expected monetary values - not ordinal priority lists or watchlists.