John works as a project manager for ABD project. He and his team, are working on the following activities: - Relative ranking or priority list of project risks - Watchlists of low priority risk Trends

The correct answer is A. Perform Qualitative Risk Analysis. Perform Qualitative Risk Analysis is the process that produces the outputs described: a relative ranking or priority list of project risks (risks ranked by probability × impact), watchlists of low-priority risks (risks too low to actively manage but worth monitoring), and trends

Perform Targeted Risk Analysis

Question

John works as a project manager for ABD project. He and his team, are working on the following activities:

  • Relative ranking or priority list of project risks
  • Watchlists of low priority risk

Trends in Qualitative Risk Analysis results On which of the following processes is John working on?

Options

  • APerform Qualitative Risk Analysis
  • BPlan Risk Management
  • CPlan Risk Responses
  • DPerform Quantitative Risk Analysis

How the community answered

(50 responses)
  • A
    90% (45)
  • B
    2% (1)
  • C
    4% (2)
  • D
    4% (2)

Explanation

Perform Qualitative Risk Analysis is the process that produces the outputs described: a relative ranking or priority list of project risks (risks ranked by probability × impact), watchlists of low-priority risks (risks too low to actively manage but worth monitoring), and trends in qualitative risk analysis results (patterns emerging over time). Plan Risk Management (B) produces the Risk Management Plan, not risk rankings. Plan Risk Responses (C) produces risk response strategies. Perform Quantitative Risk Analysis (D) produces numerical probability distributions, sensitivity analyses, and expected monetary values - not ordinal priority lists or watchlists.