The correct answer is A: Perform Qualitative Risk Analysis. See the full explanation below for the reasoning.

Perform Targeted Risk Analysis

Question

John works as a project manager for ABD project. He and his team, are working on the following activities: - Relative ranking or priority list of project risks - Watchlists of low priority risk Trends in Qualitative Risk Analysis results On which of the following processes is John working on?

Options

  • APerform Qualitative Risk Analysis
  • BPlan Risk Management
  • CPlan Risk Responses
  • DPerform Quantitative Risk Analysis

Topics

#Qualitative Risk Analysis#Risk Prioritization#Risk Watchlist#Risk Management Process