PMI-RMP · Question #249
There are five outputs of the risk monitoring and controlling process. Which one of the following is NOT an output of the process?
The correct answer is C. Vendor contracts. The Monitor and Control Risks process produces five standard outputs: Risk Register Updates, Organizational Process Assets Updates, Change Requests, Project Management Plan Updates, and Project Document Updates. Vendor Contracts (C) are an output of the Plan Procurement process,
Question
There are five outputs of the risk monitoring and controlling process. Which one of the following is NOT an output of the process?
Options
- AOrganizational process assetsupdates
- BRisk register updates
- CVendor contracts
- DChange requests
How the community answered
(24 responses)- A4% (1)
- C92% (22)
- D4% (1)
Explanation
The Monitor and Control Risks process produces five standard outputs: Risk Register Updates, Organizational Process Assets Updates, Change Requests, Project Management Plan Updates, and Project Document Updates. Vendor Contracts (C) are an output of the Plan Procurement process, not risk monitoring and controlling. Contracts are a procurement artifact used to legally bind sellers to deliver goods/services under defined terms. They have no place as an output of the risk monitoring process. The other three answer options - OPA updates (A), Risk Register updates (B), and Change Requests (D) - are all legitimate outputs of Monitor and Control Risks.
Topics
Community Discussion
No community discussion yet for this question.