PMIPMI
PMI-RMP · Question #249
PMI-RMP Question #249: Real Exam Question with Answer & Explanation
The correct answer is C: Vendor contracts. See the full explanation below for the reasoning.
Risk Monitoring and Reporting
Question
There are five outputs of the risk monitoring and controlling process. Which one of the following is NOT an output of the process?
Options
- AOrganizational process assetsupdates
- BRisk register updates
- CVendor contracts
- DChange requests
Topics
#Risk Monitoring and Controlling#Process Outputs#PMBOK Processes
Community Discussion
No community discussion yet for this question.