PMIPMI
PMI-RMP · Question #237
PMI-RMP Question #237: Real Exam Question with Answer & Explanation
The correct answer is A: Four. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
Jenny is the project manager of the NHJ Project for her company. She has identified several positive risk events within the project and she thinks these events can save the project time and money. You, a new team member wants to know that how many risk responses are available for a positive risk event. What will Jenny reply to you?
Options
- AFour
- BThree
- CSeven
- DAcceptance is the only risk response for positive risk events.
Topics
#Positive Risk Responses#Opportunity Management#Risk Response Planning#Risk Strategies
Community Discussion
No community discussion yet for this question.