nerdexam
PMIPMI

PMI-RMP · Question #236

PMI-RMP Question #236: Real Exam Question with Answer & Explanation

The correct answer is C: Cost of conformance to quality. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

You work as a project manager for BlueWell Inc. Your project is using a new material to construct a large warehouse in your city. This new material is cheaper than traditional building materials, but it takes some time to learn how to use the material properly. You have communicated to the project stakeholders that you will be able to save costs by using the new material, but you will need a few extra weeks to complete training to use the materials. This risk response of learning how to use the new materials can also be known as what term?

Options

  • ATeam development
  • BBenchmarking
  • CCost of conformance to quality
  • DCost-benefits analysis

Topics

#Risk response#Quality costs#Prevention costs#Training

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions