nerdexam
PMI

PMI-RMP · Question #229

Gary is the project manager for his project. He and the project team have completed the qualitative risk analysis process and are about to enter the quantitative risk analysis process when Mary, the…

The correct answer is C. The quantitative risk analysis process will analyze the effect of risk events that may substantially. Quantitative risk analysis numerically models the probability and impact of risk events that could substantially affect overall project objectives such as cost and schedule.

Perform Targeted Risk Analysis

Question

Gary is the project manager for his project. He and the project team have completed the qualitative risk analysis process and are about to enter the quantitative risk analysis process when Mary, the project sponsor, wants to know what quantitative risk analysis will review. Which of the following statements best defines what quantitative risk analysis will review?

Options

  • AThe quantitative risk analysis process will review risk events for their probability and impact on the
  • BThe quantitative risk analysis seeks to determine the true cost of each identified risk event and the
  • CThe quantitative risk analysis process will analyze the effect of risk events that may substantially
  • DThe quantitative risk analysis reviews the results of risk identification and prepares the project for risk

How the community answered

(22 responses)
  • B
    5% (1)
  • C
    91% (20)
  • D
    5% (1)

Why each option

Quantitative risk analysis numerically models the probability and impact of risk events that could substantially affect overall project objectives such as cost and schedule.

AThe quantitative risk analysis process will review risk events for their probability and impact on the

Reviewing individual risk events for probability and impact through subjective ratings describes qualitative risk analysis, which uses scales rather than numerical modeling.

BThe quantitative risk analysis seeks to determine the true cost of each identified risk event and the

Determining the true cost of each individual risk event is too narrow; quantitative analysis evaluates the cumulative probabilistic impact on the whole project, not just per-risk cost.

CThe quantitative risk analysis process will analyze the effect of risk events that may substantiallyCorrect

Quantitative risk analysis applies numerical techniques to assess the combined effect of identified risk events on overall project objectives, with particular focus on risks that may substantially impact total cost or schedule. It uses tools like Monte Carlo simulation and decision trees to produce probabilistic outcomes, helping stakeholders understand the range of possible project results.

DThe quantitative risk analysis reviews the results of risk identification and prepares the project for risk

Reviewing results of risk identification and preparing for risk response planning is a transition description, not the analytical purpose of quantitative risk analysis.

Concept tested: Purpose and scope of Perform Quantitative Risk Analysis

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Quantitative Risk Analysis#Risk Analysis#Risk Assessment#Project Objectives

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice