nerdexam
PMI

PMI-RMP · Question #213

In what portion of a project are risk and opportunities greatest and require intense planning and anticipation of risk events?

The correct answer is C. Initiating. Risk and opportunity are at their peak during the Initiating phase because the project is least defined, assumptions are untested, and little planning has occurred to bound uncertainty.

Risk Strategy and Planning

Question

In what portion of a project are risk and opportunities greatest and require intense planning and anticipation of risk events?

Options

  • AClosing
  • BPlanning
  • CInitiating
  • DExecuting

How the community answered

(45 responses)
  • B
    4% (2)
  • C
    93% (42)
  • D
    2% (1)

Why each option

Risk and opportunity are at their peak during the Initiating phase because the project is least defined, assumptions are untested, and little planning has occurred to bound uncertainty.

AClosing

During Closing, most work is complete and risks have largely materialized or been resolved, making the risk level at its lowest point in the project lifecycle.

BPlanning

Planning reduces uncertainty by establishing scope, schedules, and budgets, so while risk management is active in Planning, the level of unknowns is lower than in Initiating.

CInitiatingCorrect

During Initiating, the project scope, schedule, and costs are largely unknown, meaning the number of unknown variables is at its highest and the potential for both positive and negative risk events is greatest. Because detailed planning has not yet occurred, there are fewer constraints and more degrees of freedom, which simultaneously amplifies both threats and opportunities. This phase therefore demands intense anticipation and identification of risk events before commitments solidify.

DExecuting

During Executing, detailed plans exist and work is underway, so the overall uncertainty and risk exposure is lower than in the Initiating phase.

Concept tested: Project lifecycle risk exposure curve

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Project lifecycle#Risk uncertainty#Opportunity potential#Initiating phase risk

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice