nerdexam
PMI

PMI-RMP · Question #212

Mary is the project manager of PKT project. In Mary's project there are certain enterprise environmental factors that require Mary to use modeling and simulation techniques to predict the likelihood o

Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #212. The question stem and answer options stay visible for context.

Perform Targeted Risk Analysis

Question

Mary is the project manager of PKT project. In Mary's project there are certain enterprise environmental factors that require Mary to use modeling and simulation techniques to predict the likelihood of achieving cost and schedule objectives in the project. Mary is using a technique for which the cost estimates are chosen at random for each iteration of the analysis, such as pessimistic, most likely, and worst-case scenarios. What type of analysis is Mary using in this project?

Options

  • AQuantitative analysis
  • BQualitative analysis
  • CRisk distribution
  • DMonte Carlo Analysis

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Monte Carlo Analysis#Quantitative Risk Analysis#Modeling and Simulation#Cost and Schedule Risk
Full PMI-RMP Practice