PMIPMI
PMI-RMP · Question #205
PMI-RMP Question #205: Real Exam Question with Answer & Explanation
The correct answer is D: Risks in the project should be addressed by their priority for creating risk responses.. See the full explanation below for the reasoning.
Perform Targeted Risk Analysis
Question
Gary is the project manager of the MMQ project for his company. He is working with his project team to plan the risk responses for his project. Sarah, a project team member, does not understand the process that Gary is using to plan the risk responses. Which approach is the preferred method to address project risks and the risk responses?
Options
- ARisks in the project should be addressed by their probability for creating risk responses.
- BRisks in the project should be addressed by the organization's risk tolerance for creating risk
- CRisks in the project should be addressed by their impact for creating risk responses.
- DRisks in the project should be addressed by their priority for creating risk responses.
Topics
#Risk prioritization#Risk response planning#Qualitative risk analysis#Risk analysis
Community Discussion
No community discussion yet for this question.