PMI-RMP · Question #202

You work as a project manager for TechSoft Inc. You are working with the project stakeholders on the qualitative risk analysis process in your project. You have used all the tools to the qualitative…

The correct answer is C. Risk Reassessment. Risk Reassessment is a tool of Monitor and Control Risks, not of Perform Qualitative Risk Analysis, making it the one technique not applicable to qualitative analysis.

Perform Targeted Risk Analysis

Question

You work as a project manager for TechSoft Inc. You are working with the project stakeholders on the qualitative risk analysis process in your project. You have used all the tools to the qualitative risk analysis process in your project. Which of the following techniques is NOT used as a tool in qualitative risk analysis process?

Options

  • ARisk Urgency Assessment
  • BRisk Categorization
  • CRisk Reassessment
  • DRisk Data Quality Assessment

How the community answered

(62 responses)
  • A
    2% (1)
  • B
    8% (5)
  • C
    87% (54)
  • D
    3% (2)

Why each option

Risk Reassessment is a tool of Monitor and Control Risks, not of Perform Qualitative Risk Analysis, making it the one technique not applicable to qualitative analysis.

ARisk Urgency Assessment

Risk Urgency Assessment is a valid qualitative risk analysis tool used to flag risks requiring near-term responses.

BRisk Categorization

Risk Categorization is a valid qualitative risk analysis tool used to group risks by source or project area to reveal concentrations of risk.

CRisk ReassessmentCorrect

Risk Reassessment involves identifying new risks, re-evaluating current risks, and closing outdated ones - activities that belong to the Monitor and Control Risks process. The PMBOK Guide explicitly lists it as a tool of Monitor and Control Risks, not as a tool of Perform Qualitative Risk Analysis, so it is the correct answer for what is NOT used in qualitative analysis.

DRisk Data Quality Assessment

Risk Data Quality Assessment is a valid qualitative risk analysis tool used to evaluate the reliability and accuracy of risk data before using it to prioritize risks.

Concept tested: Tools and techniques of Perform Qualitative Risk Analysis

Topics

#Qualitative Risk Analysis#Risk Management Tools#PMBOK Process#Risk Reassessment