Which of the following processes must be repeated after Plan Risk Responses, as well as part of the Monitor and Control Risks, to determine if the overall project risk has been satisfactorily…

The correct answer is D. Perform Quantitative Risk Analysis. Perform Quantitative Risk Analysis must be repeated after Plan Risk Responses to verify that planned responses have adequately reduced overall project risk to an acceptable level.

Risk Monitoring and Reporting

Question

Which of the following processes must be repeated after Plan Risk Responses, as well as part of the Monitor and Control Risks, to determine if the overall project risk has been satisfactorily decreased?

Options

  • ARisk Limitation
  • BPerform Qualitative Risk Analysis
  • CIdentify Risk
  • DPerform Quantitative Risk Analysis

How the community answered

(26 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    12% (3)
  • D
    81% (21)

Why each option

Perform Quantitative Risk Analysis must be repeated after Plan Risk Responses to verify that planned responses have adequately reduced overall project risk to an acceptable level.

ARisk Limitation

Risk Limitation is not a recognized PMBOK process or standard technique used in iterative risk management cycles.

BPerform Qualitative Risk Analysis

Perform Qualitative Risk Analysis prioritizes risks by probability and impact but does not provide a quantitative measure of whether overall project risk has been sufficiently reduced.

CIdentify Risk

Identify Risks is used to discover new risks and is not the process used to verify that overall project risk exposure has been satisfactorily decreased.

DPerform Quantitative Risk AnalysisCorrect

Perform Quantitative Risk Analysis numerically analyzes the combined effect of identified risks on project objectives. After Plan Risk Responses, it is repeated to confirm that responses have reduced overall risk exposure to within acceptable thresholds. During Monitor and Control Risks, it is used again to verify that risk reduction remains sufficient as the project progresses.

Concept tested: Iterative use of Quantitative Risk Analysis post-response planning

Topics

#Quantitative Risk Analysis#Overall Project Risk#Risk Monitoring and Control#Risk Response Evaluation