PMI-RMP · Question #188
Mary is a project manager in her organization. On her current project she is working with her project team and other key stakeholders to identify the risks within the project. She is currently aiming
The correct answer is A. Brainstorming. Brainstorming is the risk identification technique that uses a facilitator to guide a group session where participants freely generate a comprehensive list of potential risks. The key distinguishing characteristics are: (1) it involves a group of people, (2) a facilitator is used
Question
Mary is a project manager in her organization. On her current project she is working with her project team and other key stakeholders to identify the risks within the project. She is currently aiming to create a comprehensive list of project risks so she is using a facilitator to help generate ideas about project risks. What risk identification method is Mary likely using?
Options
- ABrainstorming
- BDelphi Techniques
- CChecklist analysis
- DExpert judgment
How the community answered
(34 responses)- A91% (31)
- B3% (1)
- D6% (2)
Explanation
Brainstorming is the risk identification technique that uses a facilitator to guide a group session where participants freely generate a comprehensive list of potential risks. The key distinguishing characteristics are: (1) it involves a group of people, (2) a facilitator is used to manage the session, and (3) the goal is to generate as many ideas as possible without judgment. The Delphi Technique (B) uses anonymous questionnaires with expert consensus rounds - no group meeting or facilitator. Checklist Analysis (C) uses historical checklists, not idea generation. Expert Judgment (D) involves consulting individuals, not a facilitated group session.