PMI-RMP · Question #188

PMI-RMP Question #188: Real Exam Question with Answer & Explanation

The correct answer is A: Brainstorming. See the full explanation below for the reasoning.

Risk Process Facilitation

Question

Mary is a project manager in her organization. On her current project she is working with her project team and other key stakeholders to identify the risks within the project. She is currently aiming to create a comprehensive list of project risks so she is using a facilitator to help generate ideas about project risks. What risk identification method is Mary likely using?

Options

  • ABrainstorming
  • BDelphi Techniques
  • CChecklist analysis
  • DExpert judgment

Topics

#Risk Identification#Brainstorming#Facilitated Workshops#Risk Management Techniques