PMI-RMP · Question #187
Consider the risk probability-impact matrix in the figure given below: If Risk B happens in this project, how much will be left in the contingency reserve?
The correct answer is A. $193,500. This question references a probability-impact matrix figure that assigns each risk a monetary value based on probability × impact, and a total contingency reserve is established from the sum of all expected monetary values (EMV). When Risk B occurs, its full impact cost is drawn
Question
Consider the risk probability-impact matrix in the figure given below:
If Risk B happens in this project, how much will be left in the contingency reserve?
Options
- A$193,500
- B-$334,500
- CIt depends on the total budget of the project.
- D$148,300
How the community answered
(53 responses)- A85% (45)
- B6% (3)
- C8% (4)
- D2% (1)
Explanation
This question references a probability-impact matrix figure that assigns each risk a monetary value based on probability × impact, and a total contingency reserve is established from the sum of all expected monetary values (EMV). When Risk B occurs, its full impact cost is drawn from the contingency reserve. Based on the values in the referenced figure (not reproduced here), the total contingency reserve minus the cost of Risk B leaves $193,500 remaining. The correct approach is: Remaining Reserve = Total Contingency Reserve − EMV of Risk B. Option A ($193,500) is the result of that calculation per the figure's data.
Topics
Community Discussion
No community discussion yet for this question.