nerdexam
PMI

PMI-RMP · Question #187

Consider the risk probability-impact matrix in the figure given below: If Risk B happens in this project, how much will be left in the contingency reserve?

The correct answer is A. $193,500. This question references a probability-impact matrix figure that assigns each risk a monetary value based on probability × impact, and a total contingency reserve is established from the sum of all expected monetary values (EMV). When Risk B occurs, its full impact cost is drawn

Risk Monitoring and Reporting

Question

Consider the risk probability-impact matrix in the figure given below:

If Risk B happens in this project, how much will be left in the contingency reserve?

Options

  • A$193,500
  • B-$334,500
  • CIt depends on the total budget of the project.
  • D$148,300

How the community answered

(53 responses)
  • A
    85% (45)
  • B
    6% (3)
  • C
    8% (4)
  • D
    2% (1)

Explanation

This question references a probability-impact matrix figure that assigns each risk a monetary value based on probability × impact, and a total contingency reserve is established from the sum of all expected monetary values (EMV). When Risk B occurs, its full impact cost is drawn from the contingency reserve. Based on the values in the referenced figure (not reproduced here), the total contingency reserve minus the cost of Risk B leaves $193,500 remaining. The correct approach is: Remaining Reserve = Total Contingency Reserve − EMV of Risk B. Option A ($193,500) is the result of that calculation per the figure's data.

Topics

#Contingency Reserve#Risk Response#Financial Impact#Risk Monitoring

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice