nerdexam
PMIPMI

PMI-RMP · Question #187

PMI-RMP Question #187: Real Exam Question with Answer & Explanation

The correct answer is A: $193,500. See the full explanation below for the reasoning.

Risk Monitoring and Reporting

Question

Consider the risk probability-impact matrix in the figure given below: If Risk B happens in this project, how much will be left in the contingency reserve?

Options

  • A$193,500
  • B-$334,500
  • CIt depends on the total budget of the project.
  • D$148,300

Topics

#Contingency Reserve#Risk Response#Financial Impact#Risk Monitoring

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions