PMIPMI
PMI-RMP · Question #187
PMI-RMP Question #187: Real Exam Question with Answer & Explanation
The correct answer is A: $193,500. See the full explanation below for the reasoning.
Risk Monitoring and Reporting
Question
Consider the risk probability-impact matrix in the figure given below: If Risk B happens in this project, how much will be left in the contingency reserve?
Options
- A$193,500
- B-$334,500
- CIt depends on the total budget of the project.
- D$148,300
Topics
#Contingency Reserve#Risk Response#Financial Impact#Risk Monitoring
Community Discussion
No community discussion yet for this question.