nerdexam
PMIPMI

PMI-RMP · Question #170

PMI-RMP Question #170: Real Exam Question with Answer & Explanation

The correct answer is B: Opportunities. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

Thomas is the project manager of the NHJ Project for his company. He has identified several positive risk events within his project and he thinks these events can save the project time and money. Positive risk events, such as these within the NHJ Project are also known as what?

Options

  • ABenefits
  • BOpportunities
  • CAncillary constituent components
  • DContingency risks

Topics

#Positive risk events#Opportunities#Risk definition

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions