PMIPMI
PMI-RMP · Question #170
PMI-RMP Question #170: Real Exam Question with Answer & Explanation
The correct answer is B: Opportunities. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
Thomas is the project manager of the NHJ Project for his company. He has identified several positive risk events within his project and he thinks these events can save the project time and money. Positive risk events, such as these within the NHJ Project are also known as what?
Options
- ABenefits
- BOpportunities
- CAncillary constituent components
- DContingency risks
Topics
#Positive risk events#Opportunities#Risk definition
Community Discussion
No community discussion yet for this question.